Quick links
|
||
|
14th February 2007 The land filling for the station and ride area has begun.
19th February 2008
The land filling is almost complete. Also a trench has been dug going towards the ride area, this will probably be to hold cables needed for the ride. 29th May 2008
Land filling is now complete and trees have been cut down in the new ride area. Construction is due to begin soon. 28th August 2008
All the trees have now been cleared. Steel for the ride footers and station foundations have been put in the ground and some concrete has been poured. Also signs promoting the new ride have appeared around the park. 16th October 2008
The track has been fully erected and the stations frame is complete. Also new signs promoting the ride have gone up around the park. 18th February 2009
The ride is currently on set to be open on 14th March. The staition building is now complete and a lot of themeing has been added with still more to come. Also the ride has been testing a lot recently. Click Here to see a video of the ride testing. |
|
© Copyright Thorpe park data 2009. The official site can be found by clicking here.
|